Mining Pump Pontoon Extend Modification Project

Project Name : Mining Pump Pontoon Extend Modification
Project Duration : April - June 2013

Reason / Issue : This old pontoon not suit with new bigger Mining Pump.
Solution : Modificate old pontoon to suit with new Mining Pump.

Goal / Target :
- This old pontoon will operate with new Mining Pump.
- Pontoon could used in pond or on ground.
- Pontoon will able to used for more than 5 years.

Process :
- Redesign pontoon with updated engineering calculation.
- Fabricate Additional Pontoon which fit permanently with old pontoon.
- Performance Test
- Assessment

Data :
- Pontoon design original












- Pontoon design after extended modification

Project Result : Success

Hi Engineers, Welcome to My Blog...

Hi, hello there...
My name is Puraditya and you can call me just Pura.

Currently I work as Plant Engineer at International Mining Contractor which located in Kalimantan, Indonesia. Mining industry is one of industry which have high standard in safety and efficiency. There a lot of challenge in this industry area between in plant workshop or in mining pit field. As engineer, we could give most effective and efficient solution.

My friend Aldi and Me at my workplace

I will share few of my experiences and my engineering project when I work at site. All picture, drawing and files in this blog is for preliminary reference only. Always do engineering calculation and check with engineering standard by your own.

I hope with this blog I could share and discuss any idea and innovation with always better and keep move forward.

Salam Engineer,
Puraditya