Project Duration : April - June 2013
Reason / Issue : This old pontoon not suit with new bigger Mining Pump.
Solution : Modificate old pontoon to suit with new Mining Pump.
Goal / Target :
- This old pontoon will operate with new Mining Pump.
- Pontoon could used in pond or on ground.
- Pontoon will able to used for more than 5 years.
Process :
- Redesign pontoon with updated engineering calculation.
- Fabricate Additional Pontoon which fit permanently with old pontoon.
- Performance Test
- Assessment
Data :
- Pontoon design original
- Pontoon design after extended modification
Project Result : Success